Tuesday, January 27, 2009

Waiting On Metal Roofing

We are really getting excited! We now have windows and doors, and as you can see, the siding is nearly all installed. The roof is waiting on the metal to be delivered, and the plumbers were on-site today beginning their top-out. It also rained a bit today but not enough to do any damage.


Siding is up and the roof just needs some metal.














Here's the Watts Enterprise team. Linda bought T-shirts for us. So we donned them and went to dinner to celebrate.


Monday, January 19, 2009

Getting Near To Drying

Well we are approaching the point where we close in everything so we can stop worrying about weather. As you can see, the roof trusses were delivered, the crew we hired erected them and are beginning to put decking on the roof and put up soffits. Linda and Sharon installed hurricane straps on the roof trusses. Carl is inside the trailer working on the computer to try to pay for the help, and Maxie is continuing to manage the project. We are very excited about the progress.