Many have asked how the house is coming, so here is the progress to date:
  • we have a set of house plans;
  • we have approval of the plans from our Architectural Control Committee;
  • we have a site plan;
  • the land is cleared;
  • we have water and electricity;
  • we have a septic permit and septic plan;
  • we have a driveway permit; and
  • we have estimates for the plumbing and electrical work in the house.
This doesn't seem like much progress, but we feel good about where we are.

Next steps are:
  1. gather remaining building cost estimates;
  2. have the property surveyed; and
  3. complete application for construction loan.